Monday, February 15, 2010
Insulation and Plastering
By Friday afternoon most of the outside wall insulation had been installed with a reasonable amount of plastering too. All the ceiling is now plastered. Rooms are really taking some shape now.

Half way there
Saturday, February 6, 2010
It's a big hole!
Thursday, February 4, 2010
Big toys and lining
Today we had a couple of deliveries to the house - more plaster board, cornices and a tonka truck! This means the plumbing passed its first inspection, and we should have a dirty big hole for our water tank in the next few days.
We have been advised that it usually takes a week to get the underground cement water tank done, so keep checking back to see the progress!
Monday, February 1, 2010
Electrical and Plumbing!
Alright, so its been over two weeks......
The electrical cables, water and gas plumbing have now been installed. Even the air-con is there. According to Steve a plumbing inspection is due this week after which (assuming it passes) the walls and ceiling insulation shall be installed followed by the plasterboard.
Today the batons for the ceilings where nailed in (sorry no photos of those yet). The cornices where also delivered. Soon will look like a house on the inside as well as the outside!


The electrical cables, water and gas plumbing have now been installed. Even the air-con is there. According to Steve a plumbing inspection is due this week after which (assuming it passes) the walls and ceiling insulation shall be installed followed by the plasterboard.
Today the batons for the ceilings where nailed in (sorry no photos of those yet). The cornices where also delivered. Soon will look like a house on the inside as well as the outside!
Tuesday, January 12, 2010
Finally - some new photos.
The roof and bricking is now complete. They also cleaned up most of the mess left around which is nice (still missing quite an amount mind you). Still not at lock up stage, but hopefully not far away.




The roof and bricking is now complete. They also cleaned up most of the mess left around which is nice (still missing quite an amount mind you). Still not at lock up stage, but hopefully not far away.
The sliding doors rails were installed just before Christmas.
A spectacular view of the interior!
The interior of the garage.
A view looking at the south-east side of the house.
And the north-east view.